Summer Construction 2023

Air-Conditioning Update: August 2023

DISTRICT RENOVATIONS: Summer 2023

Balmoral Elementary

  • Adding new HVAC heating and air conditioning
  • Asbestos abatement
  • New flooring in the classrooms

Crete Elementary

  • Adding new HVAC heating and air conditioning
  • Asbestos abatement
  • New flooring in the classrooms

Coretta Scott King Magnet School

  • Adding new HVAC heating and air conditioning
  • Asbestos abatement
  • New flooring in the classrooms

Talala Elementary

  • Asbestos abatement
  • New flooring in the classrooms

Crete-Monee High School Addition

Future home of programs such as participation in the classroom community model, individualized academic programming (IAP), social and emotional support, vocational training, transitioning back to home school, student transition educational placement services, students with an individualized education plan (IEP), credit recovery, and crisis intervention behavior stabilization (CIBS) as well as the manufacturing programs. This is projected to be completed on October 15, 2023.

Updates include:

  • Cold formed steel framing at the manufacturing lab for ACM panels
  • Wood blocking installation
  • Welding booths and partition walls have been installed
  • Roof deck installation is complete and the roofing system installation has begun
  • Air barrier membrane installation is in progress for window framing and roof edge
  • Electrical, plumbing, piping, and storm water piping is on-going
  • Concrete masonry unit installation has begun on interior walls
  • Openings for ductwork have been installed

New Central Office Building
690 W. Exchange St., Crete, IL 60417

  • New flooring
  • Building renovations